bracing to make sure they did not get destroyed in the trip. Everything was fastened down either by cable or in big boxes that was sealed up and tied up to the structure of the building. The doors were all inside these big wood crates and the hardware was in smaller crates beside them. Everything was marked. The grating for the cat walks was banded down in bundles on some of the framework. The stairs were all in place as was most of the piping and electrical. After we got the doors all on and the grating all set the trades began to do the hook up of all the parts in the modular building. Lots of electrical go the power rooms, and the piping needed to be connected to the different phases of the process. These buildings were very cold as there was no heat yet and everything felt frozen. Inside it seemed like there must have hundreds of miles of pipe and grading catwalks everyplace. We also saw some big vessels where the oil was going to be cleaned up before being pumped to the pipeline. We had to go inside a few of these big tanks and erect scaffolding so
they could put more finish coats inside these tanks to keep the oil from eating trough the skin. Everything was so large I had never been around anything with piping like this before. They also had these huge electrical rooms and there was conduit that ran everyplace. The electricians also came in with us to get the power ready to start so we could warm these buildings up and get them ready to go online. These huge modular buildings were carried by a machine called a creepy crawler to where they were set. A creepy crawler was the frame of a huge track type crane and in the middle of the body was this huge piston that could lift or lower the buildings on to the pilings. Some of the buildings had 4, 5 or 6 of these creepy crawlers caring them from the Arctic Ocean to the site. (Picture of a creepy crawler setting a smaller building)
The pilings had a gravel mound built up around them, and the crawlers climbed up the mounds and sat the buildings then drove off the mound on the other side. After the building was all set the laborers started clearing out the mounds of gravel so we had the clearance needed under the buildings. Before the put the stairs up to get in we climbed up ladders to open up the units. The reason they were put on high piling was when it snowed up there the wind would blow and blow (seems it blows 24 hours a day 7 days a week all year long) and the snow would build up and cover the buildings. So by putting them on the piling the snow would drop when it hits the side and blow away under the buildings. The buildings were full of huge tanks, piping and everything that a gathering center would need to gather the oil and clean it up some and add the additives to the oil and send it to the pipeline. The remainder of the buildings was to be set this coming year and finished the next year.
Page One ~
Page Two ~
Page Three ~
Page Four ~
Page Five ~
Page Six
~
Page Seven ~
Page Eight ~
Page Nine ~
Page Ten
Content and Design is the copyright © of Bernard Howe 1997 - 2004