
Trestles RGS Style
Wooden Trestle Construction
on the Rio Grande Southern Railroad
by Bob Hyman

Part 1 - Prototype Trestles
Introduction
When completed, the Rio Grande Southern Railroad had 142
bridges scattered along its 162 miles of track. Almost all of the original
bridges were rebuilt or replaced at one time or another. The early Howe truss
bridges were replaced with simple open deck trestles, and many of the smaller
bridges were replaced with earthen fills and culverts. By the end of operations,
111 bridges were left on the railroad; virtually none were original. The reasons
for replacing a bridge were many, but for the most part, the arrival of heavier
motive power or damage caused by weather and high water resulted in replacement.
(Click on images for larger versions.)
Figure
1 - Bridge 51-A (Lake Fork Trestle)
At first glance, most of the trestles appear to be similar.
However, a closer look shows that all differ in detail. The RGS built its
bridges following accepted and proven engineering practices, but did not adhere
to strict standardization. Thus, all of the bridges look similar in overall
design, but still have individual characteristics. Some detail differences in
the bridges occurred due to unusual circumstances in placement or geography.
Other differences were due to the availability of materials and the financial
status of the line when repairs were made. Changes also occurred depending on
what practices were in favor when the bridges were repaired. Thus, over time,
all of the bridges slowly changed.
This handout details some of the basic design standards and
building techniques that the trestles adhered to, no matter their differences in
detail. It explores some of the more obvious differences, particularly on the
large timber trestles on the high line over Lizard Head Pass between Vance
Junction and Rico. In addition to explaining prototype construction methods,
techniques are presented for building accurate scale models of these trestles.
Basic Trestle Components
A trestle is composed of an open, braced wooden framework
that supports the railroad above ground level. It consists of a series of
identical (or nearly so) vertical supports holding up a succession of short
spans. All wood portions of a trestle are designed to be in compression and
never in tension.
Bents
The deck of a trestle is supported by vertical structures
called bents. There are two types of bents. The pile bent has round
posts, usually twelve inches in diameter, which are driven directly into the
ground. The frame bent has square posts sitting on a horizontal bottom
support member called a sill. The sill usually rests on a separate
foundation. Both types of bents have a horizontal cap resting on top of
the posts. The cap equally distributes the load from the bridge deck above to
the posts below. The space between two adjacent bents is called a panel.
(Click on image for larger version.)
Figure
2 - Typical Bent Components
There are a minimum of four posts in a bent two
(sometimes three) inner posts and two outer posts. The inner posts are usually
(but not always) vertical. The outer posts are angled 2" to 3" per
foot. This angle is called batter. Additional intermediate posts may be
present in the bent between the inner and outer posts. These are also battered,
either at the same angle as the outer posts, or at some lesser angle. Batter is
expressed as a ratio of spread to height, e.g., 2 in 12 or 3 in 12.
Pile bents were not made higher than thirty feet due to the
length of available wood material (generally no longer than 60 feet). This is
because each pile is a single piece, and a sizeable portion of it must be driven
into the ground. Also, the round configuration is not easily adapted to the
construction of tall trestles. Piles were always driven with the narrow diameter
down.
Frame bents were typically built from around five to a
maximum of thirty feet tall, also due to the length of available posts. If a
taller trestle was required, the bents were divided into stories,
separated by horizontal intermediate 12"-square sills. In normal practice,
the bent heights varied as necessary for the bridge to fit into the terrain. For
heights under 16 to 20 feet, one story was used. For heights over this, anywhere
from two to five stories would be used; the upper stories were normally the full
height and the bottom one was adjusted to fit as necessary.
Bracing
Most bents have diagonal sway bracing for reinforcement.
These sway braces are lengths of 3" x 10" or 3" x 12" lumber
attached to the cap, posts and sill at an angle somewhere between 30 and 60
degrees. Sway bracing typically runs from upper-right to lower-left, although
many reversed examples are found. The ends of the sway braces were sometimes cut
at an angle to match the ends of the caps and sills; others were left as normal
perpendicular cross cuts. If the distance from corner to corner of the bent was
longer than the available bracing boards, two boards would be used. The RGS
bridge crews were very resourceful when it came to using whatever material was
available to get the job done!
Occasionally, bents have horizontal 3" x 12" braces
on each side of the bent about halfway between the cap and the sill. These
horizontal braces are called sashes. Although sash bracing is common on
pile bents, it is rarely used on frame bents. Bridge 58-A, the Meadow Creek
Trestle, and Bridge 51-A, the Lake Fork Trestle, are notable exceptions.
To make a trestle rigid along the length, horizontal timbers
called girts are placed on top of the sills or sashes, and connect each
bent to the next. When extra longitudinal stiffness is required, the bents are
connected with wall bracing. This bracing lies parallel to the sides of
the trestle and connects the posts of adjacent bents with crossed pieces. Wall
bracing is generally the same size as sway bracing. The RGS did not use wall
bracing often; a notable exception is Bridge 58-A.
Foundations
The bottom sill of a frame bent is called a mud sill.
It may rest on a variety of foundations. Some trestles had the mud sill attached
to the tops of piles driven into the ground. Others rested on blocks of used
bridge timbers, typically 8" x 18" x 3 feet (see Figure 3).
Occasionally a mud sill would rest directly on the ground. In the later years,
poured concrete was common (see Figure 4).
(Click on image for larger version.)
Figure
3 - Bridge 57-A Timber Block Foundation
(Click on image for larger version.)
Figure
4 - Bridge 45-A Poured Concrete Foundation
Deck
The deck of a trestle starts with wooden stringers set on top
of the bent caps. The bents were generally placed 16 feet apart, with stringers
of 8" x 18". If the bents needed to be farther apart, stringer size
was increased to 8" x 24". Standard 8" x 18" stringers were
32 feet long and spanned two panels. Three stringers were bolted together into a
single beam, leaving a 1 ½" space between the individual stringers for
ventilation. Two beams were placed side-by-side, about two feet apart, on the
caps. Bridge ties were laid on the stringers, and guard timbers ran the length
of the deck at the tie ends. The guard timbers were usually notched to fit over
the tie ends and hold them in alignment. Galvanized sheet metal was placed on
the tops of the bent caps and on the tops of the stringers to protect the wood
from falling cinders. Running rails, gauged at three feet, were spiked to every
tie. Guard rails, when used, were generally spiked to every fourth tie.
Initially, the guard rails were located inside of the running rails. Later, they
were moved outside of the running rails, probably to provide clearance for blade
flangers.
Design and Materials
The drawings at the end this handout represent typical
multi-story bents from curved, tangent and compound (both curved and tangent)
RGS trestles. Tangent trestles were generally built with a batter, or slope, of
2 in 12 on the outer posts, while curved trestles had a batter of 3 in 12. The
drawings show the height of each story. Two major styles of trestle bents were
used on the RGS. One style used two vertical posts in the center and the other
used three. Some trestle bents were built without vertical posts, and used 1 in
12 batter for the inner posts.
Construction Details
The prototype photos in this handout show timber remnants
from RGS trestle sites. Bridge 51-A is the only one of the large RGS trestles
still standing. It was maintained for a while after abandonment by the state of
Colorado, but for the most part, it exists today just as it did when the RGS ran
trains over it. The dimensions of the wooden members of this bridge are
consistent with normal railroad practice, and the metal hardware used to tie the
bridge together is basically the same as observed in the remains of many other
bridges.
Construction Methods
Figure 5 shows the method generally used by the RGS to tie
trestle components together. This style of construction has been observed at
some of the major bridge sites on the railroad that contain enough material for
examination. It is also evident in the water towers still standing.
(Click on image for larger version.)
Figure
5 - Construction Details (Typical)
The cap was attached to the posts underneath it by driving a
round 3/4" diameter x 24" long steel drift pin down through the cap
and into the post. This was done for each post and for each story of every bent.
The deck beams were attached to the caps by driving a round 3/4" diameter x
30" long steel drift pin down through the stringers and into the cap.
(Click on image for larger version.)
Figure
6 - Stringer Connection Details (Tangent Trestle)
The individual stringers making up each beam were typically
32 feet long and spanned two panels. The ends of the stringers were staggered as
shown in Figures 6 and 7. The stringers were bolted together with 3/4"
diameter x 30" long bolts, 2" washers and nuts. On a tangent trestle,
the stringers making up the beams were parallel to each other (see Figure 6). 1
1/2" x 3 1/2" packing washers were placed on the bolts between the
stringers to maintain spacing. If the trestle was on a curve, the stringers
making up each beam were not parallel to each other, but were angled as shown in
Figure 7.
(Click on image for larger version.)
Figure
7 - Stringer Arrangement (Curved Trestle)
The ties were typically attached to the beams with 5/8"
diameter x 12" long Lewis lag screws. The screws were placed in every third
tie on tangents and curves up to three degrees, and in every other tie on curves
over three degrees.
(Click on image for larger version.)
Figure
8 - Guard Timber Details
The notched guard timbers were typically screwed to every fourth tie with
5/8" diameter x 8" long Lewis lag screws, except at lap joints where
two guard timbers were spliced together. At lap joints, the two guard timbers
were attached to the tie with a 3/4" diameter x 12" bolt, 2"
washer and nut. Figure 9 shows deck details of Bridge 51-A.
(Click on images for larger
versions.)
Figure
9 - Deck Detail Photos
Anywhere from one to three small bridge nails (8" or 9" long with
3/8" shaft) were used to attach the sway braces to the posts. These are
often called boat spikes. Boat spikes are found with both circular and
square cross-sections. The sway braces usually ran from the lower left to upper
right. This unit or story was often assembled off to the side and then moved
into position on the bridge. Figure 10 shows bridge nails in a sill of Bridge
44-A (Butterfly Trestle). Note how sill was notched at lap joint. Extended nails
show where a post was toe-nailed to the sill.
(Click on image for larger version.)
Figure
10 - Bridge Nail Photo
Each story was attached to the one below by toe-nailing several full sized
bridge nails through the post and into the cap of the story underneath. In the
bottom story, the mud sill would probably be attached before the story was moved
into place. As each story was positioned and attached to the story below, girts
were added between the bents to stabilize them. When finished these bridges were
strong and stable. The bridge at Ames, (43A), which was built in a very
precarious location, stood for almost thirty years after abandonment with no
maintenance whatsoever.
Materials Used